May 2011 - December 2016

Misc. Capital Engineering and Construction Projects

Specializing in project execution of small capital projects at Wheelabrator’s fleet of power plants. Developed a method of planning and execution that proved successful in delivering projects on-time and on-budget while minimizing impact to facility operations and availability.


 
 
20140326_181945.jpg

Bridgeport metals recovery / ash handling system modifications

Wheelabrator Bridgeport - Bridgeport, CT - 67 MW, 2,250 TPD Energy-FROM-WASTE Power Plant

Total Project Cost: $1,200,000 – 21.5% IRR, improved non-ferrous recovery revenues

• Project Engineer/Project Manager for the modification of an existing metals recovery and ash processing system at the WTI Bridgeport Facility

• Developed strategy to minimize system downtime during construction. 9 day system outage

• Project successful; on-time and on-budget

 
20130611_101418.jpg

Westchester Export steam line / chp conversion

WHEELABRATOR Westchester - Peekskill, NY - 60 MW, 2,250 TPD Energy-FROM-WASTE Power Plant

Total Project Cost: $2,900,000 – 23.5% IRR, new steam sales revenues

• Project Engineer/Project Manager for the installation of an entirely new export steam line from the WTI Westchester Facility to a neighboring industrial laundry facility

• Managed the procurement process for the selection of a design-build (EPC) contractor

• Managed system start-up team and turn-over to the facility

• Project successful; on-time and on-budget

 
20130517_113428.jpg

Concord metals recovery / ash handling system modifications

Wheelabrator Concord - Penacook, NH - 14 MW, 500 TPD Energy-from-waste Power Plant

Total Project Cost: $4,300,000 – 15.5% IRR, new ferrous and non-ferrous scrap metal sales revenues

• Project Engineer/Project Manager for the installation of an entirely new metals recovery and ash processing system at the WTI Concord Facility

• Developed strategy to minimize system downtime during construction

• Worked with plant personnel, consulting engineers, and equipment suppliers to design the system in the most cost effective and practical layout

• Project successful; on-time and on-budget